What you are applying forآپ کس چیز کے لیے درخواست دے رہے ہیں
S.R.O. 251(I)/2026, the National Electric Power Regulatory Authority (Prosumer) Regulations, 2026, was notified on 9 February 2026. Regulation 14 is the billing rule. At the end of each billing cycle the distribution company bills the electricity you consume at the applicable tariff, and it credits the kilowatt-hours you supply to the company at the national average energy purchase price. The regulations name that arrangement net billing. They do not print a rupee export rate. The calculator on this site therefore keeps two reported rupee figures beside the rule: Rs 8.13 as a reported energy-purchase component, and about Rs 11 as the figure officials gave reporters in February 2026. Neither is a number inside regulation 14. Type the rate you have been given when you have one.ایس آر او 251(I)/2026، نیپرا پروزیومر ریگولیشنز 2026، 9 فروری 2026 کو نوٹیفائی ہوئیں۔ ریگولیشن 14 بلنگ کا قاعدہ ہے۔ ہر بلنگ سائیکل کے آخر میں ڈسکو آپ کی کھپت قابلِ اطلاق ٹیرف پر بل کرتی ہے، اور جو کلوواٹ آور آپ کمپنی کو دیتے ہیں انہیں قومی اوسط توانائی خرید قیمت پر کریڈٹ کرتی ہے۔ ریگولیشنز اس بندوبست کو نیٹ بلنگ کہتے ہیں۔ وہ روپے کی برآمدی شرح نہیں چھاپتے۔ اس سائٹ کا کیلکولیٹر قاعدے کے ساتھ دو رپورٹ شدہ روپے رکھتا ہے: 8.13 بطور رپورٹ شدہ توانائی خرید جزو، اور تقریباً 11 وہ عدد جو حکام نے فروری 2026 میں رپورٹرز کو دیا۔ دونوں ریگولیشن 14 کے اندر نہیں۔ جو شرح آپ کو ملی ہو وہ لکھیں۔
The same regulations repeal the 2015 net-metering rules, with an important later correction. Read on its own, regulation 21 of the February text moved existing agreements onto a national average power purchase price. S.R.O. 547(I)/2026, dated 2 April 2026 and deemed effective from 9 February 2026, amends that position: agreements signed under the 2015 rules keep that mechanism until they expire, unless the maximum output changes. A household with a live 2015 agreement should not assume the February text cancelled it on the day the new regulations were notified. A household applying now is in the new arrangement.یہی ریگولیشنز 2015 کے نیٹ میٹرنگ قواعد منسوخ کرتے ہیں، بعد کی اہم درستگی کے ساتھ۔ تنہا پڑھا جائے تو فروری کے متن کی ریگولیشن 21 موجودہ معاہدوں کو قومی اوسط پاور پرچیز پرائس پر لے جاتی تھی۔ ایس آر او 547(I)/2026، مورخہ 2 اپریل 2026 اور اثر 9 فروری 2026 سے، وہ پوزیشن بدلتا ہے: 2015 کے تحت دستخط شدہ معاہدے اس طریقے پر رہتے ہیں جب تک ختم نہ ہوں، جب تک زیادہ سے زیادہ آؤٹ پٹ نہ بدل جائے۔ زندہ 2015 معاہدہ والا گھر یہ نہ مانے کہ فروری کے متن نے نوٹیفکیشن کے دن اسے ختم کر دیا۔ اب درخواست دینے والا نئے بندوبست میں ہے۔
The limit that comes before the formفارم سے پہلے کی حد
Regulation 3 says the capacity of the proposed distributed generation facility shall not exceed the sanctioned load of the premises. The Authority may revise that cap by a later notification. Until it does, a 7 kilowatt array on a 5 kilowatt sanctioned load does not get through this clause by being called a future upgrade. If the roof can hold more than the sanctioned load, the load is raised with the distribution company first, as a separate application, and only then does the generation capacity follow. The five-year term in regulation 7 runs from commissioning, and it can be renewed for another five years by mutual consent. The term is not a reason to oversize the first application.ریگولیشن 3 کہتی ہے مجوزہ ڈسٹری بیوٹڈ جنریشن کی گنجائش احاطے کے منظور شدہ لوڈ سے زیادہ نہیں ہو گی۔ اتھارٹی بعد کی نوٹیفکیشن سے یہ حد بدل سکتی ہے۔ جب تک نہ بدلے، 5 کلوواٹ منظور شدہ لوڈ پر 7 کلوواٹ سرنی اس شق سے اس لیے نہیں گزرتی کہ اسے مستقبل کا اپ گریڈ کہا جائے۔ اگر چھت لوڈ سے زیادہ رکھ سکے تو لوڈ پہلے ڈسکو سے بڑھایا جاتا ہے، الگ درخواست کے طور پر، اور اس کے بعد جنریشن کی گنجائش آتی ہے۔ ریگولیشن 7 کی پانچ سالہ مدت کمیشننگ سے چلتی ہے، اور باہمی رضا سے مزید پانچ سال تجدید ہو سکتی ہے۔
Two further gates sit in the same regulation. An applicant proposing 250 kilowatts or more must submit a load-flow study carried out through the licensee or a consultant registered with the Pakistan Engineering Council. A house is nowhere near that threshold, but a commercial premises can be. Separately, the licensee shall not entertain an application if the distributed generation already connected to a particular distribution transformer has reached 80 percent of that transformer's rated capacity. That refusal is about the transformer, not about your paperwork. No calculator on this site can see the transformer.اسی ریگولیشن میں دو اور دروازے ہیں۔ 250 کلوواٹ یا زیادہ کی تجویز والا درخواست دہندہ لوڈ فلو مطالعہ جمع کرائے، لائسنسی کے ذریعے یا پاکستان انجینئرنگ کونسل کے رجسٹرڈ مشیر سے۔ گھر اس حد کے قریب نہیں، تجارتی احاطہ ہو سکتا ہے۔ الگ، لائسنسی درخواست نہیں لے گا اگر کسی ڈسٹری بیوشن ٹرانسفارمر پر جڑی ڈسٹری بیوٹڈ جنریشن اس ٹرانسفارمر کی ریٹڈ گنجائش کے 80 فیصد تک پہنچ چکی ہو۔ یہ انکار ٹرانسفارمر کا ہے، کاغذوں کا نہیں۔ اس سائٹ کا کوئی کیلکولیٹر ٹرانسفارمر نہیں دیکھ سکتا۔
The timeline regulation 3 actually printsوہ مدت جو ریگولیشن 3 واقعی چھاپتی ہے
The application goes to the licensee, which for a house is the distribution company, on the form specified as Schedule II. The licensee is bound to provide information and the Authority's approved documents, free of cost, within two working days of a request. Within five working days of receiving the application the licensee acknowledges it and says whether it is complete. Missing information has to come back within three working days of that message. Once the file is complete, the initial technical review is to be finished within fifteen working days. If the review says the facility is not technically feasible, the licensee returns the application and gives reasons within three working days after the review.درخواست لائسنسی کے پاس جاتی ہے، گھر کے لیے ڈسکو، اس فارم پر جو شیڈول II ہے۔ لائسنسی معلومات اور اتھارٹی کے منظور شدہ دستاویزات مفت، درخواست کے دو کام کے دنوں میں دینے کا پابند ہے۔ درخواست ملنے کے پانچ کام کے دنوں میں لائسنسی وصولی تسلیم کرتا ہے اور بتاتا ہے مکمل ہے یا نہیں۔ غائب معلومات اس پیغام کے تین کام کے دنوں میں واپس آنی ہوتی ہیں۔ فائل مکمل ہونے پر ابتدائی تکنیکی جائزہ پندرہ کام کے دنوں میں ختم ہونا ہے۔ اگر جائزہ کہے سہولت فنی طور پر ممکن نہیں، لائسنسی درخواست واپس کرتا ہے اور جائزے کے بعد تین کام کے دنوں میں وجوہات دیتا ہے۔
If the licensee is satisfied, the agreement is signed within seven working days, and a copy goes to the Authority within seven working days of signing. Within seven working days of the agreement the licensee issues the connection-charge estimate for the interconnection facility up to the interconnection point, including the meter. The prosumer pays that estimate within seven working days of its issue. The licensee installs and commissions the facility within fifteen working days of that payment. Those are working days in the regulation, not a promise that every office hits them. They are also the whole of the step list this guide will defend, because they are the steps the notification writes down. A portal screen, a witness, or a particular stamp paper is a company's practice on top of this list. This site has not copied one company's portal and called it national.اگر لائسنسی مطمئن ہو تو معاہدہ سات کام کے دنوں میں دستخط ہوتا ہے، اور نقل دستخط کے سات کام کے دنوں میں اتھارٹی کو جاتی ہے۔ معاہدے کے سات کام کے دنوں میں لائسنسی کنکشن چارج کا تخمینہ جاری کرتا ہے، میٹر سمیت۔ پروزیومر وہ تخمینہ اجرا کے سات کام کے دنوں میں ادا کرتا ہے۔ لائسنسی ادائیگی کے پندرہ کام کے دنوں میں سہولت لگاتا اور کمیشن کرتا ہے۔ یہ ریگولیشن کے کام کے دن ہیں، یہ وعدہ نہیں کہ ہر دفتر انہیں پورا کرتا ہے۔ یہی وہ فہرست ہے جس کا یہ گائیڈ دفاع کرے گی، کیونکہ یہ وہ مراحل ہیں جو نوٹیفکیشن لکھتی ہے۔ پورٹل کی سکرین یا خاص اسٹامپ پیپر اس فہرست کے اوپر کمپنی کا طریقہ ہے۔ اس سائٹ نے ایک کمپنی کا پورٹل نقل کر کے اسے قومی نہیں کہا۔
Who approves, and what the fee isمنظوری کون دیتا ہے، اور فیس کیا ہے
Regulation 4, as first notified, required the prosumer to seek the Authority's concurrence, with the agreement, evidence of the fee, and an affidavit forwarded by the licensee. The fee was then set by the notification of 28 April 2026 under Schedule IV, deemed effective from 9 February 2026. That notification says an application for concurrence is accompanied by no fee when the facility is 25 kilowatts or less, and by Rs 1,000 per kilowatt, paid in favour of the Authority, when the facility is above 25 kilowatts. The rate file on this site stores the same split: free up to 25 kilowatts, then Rs 1,000 per kilowatt.ریگولیشن 4، جیسا کہ پہلے نوٹیفائی ہوئی، پروزیومر سے اتھارٹی کی منظوری مانگتی تھی، معاہدے، فیس کے ثبوت، اور حلف نامے کے ساتھ جو لائسنسی آگے بھیجے۔ فیس پھر 28 اپریل 2026 کی نوٹیفکیشن نے شیڈول IV کے تحت رکھی، اثر 9 فروری 2026 سے۔ وہ نوٹیفکیشن کہتی ہے منظوری کی درخواست کے ساتھ فیس نہیں جب سہولت 25 کلوواٹ یا کم ہو، اور 1,000 روپے فی کلوواٹ، اتھارٹی کے حق میں، جب سہولت 25 کلوواٹ سے اوپر ہو۔ اس سائٹ کی ریٹ فائل وہی تقسیم رکھتی ہے۔
A later file on NEPRA's site, S.R.O. 1330(I)/2026 dated 6 August 2026, says a system of 25 kilowatts or below does not need the Authority's concurrence. The distribution company approves it. Some reports call that file S.R.O. 1320(I)/2026. The file name on the Authority's site is 1330, and that is the name this guide uses. Read together, a house-scale system is a distribution-company approval with a nil concurrence fee, and a system above 25 kilowatts still goes to the Authority with Rs 1,000 per kilowatt. The connection-charge estimate in regulation 3 is a different bill. It pays for the meter and the interconnection the company builds. The regulations do not print that estimate as a national rupee figure, so this guide does not invent one.نیپرا کی سائٹ پر بعد کی فائل، ایس آر او 1330(I)/2026 مورخہ 6 اگست 2026، کہتی ہے 25 کلوواٹ یا کم کے سسٹم کو اتھارٹی کی منظوری نہیں چاہیے۔ ڈسکو منظور کرتی ہے۔ کچھ رپورٹیں اس فائل کو 1320 کہتی ہیں۔ اتھارٹی کی سائٹ پر فائل کا نام 1330 ہے، اور یہ گائیڈ وہی نام استعمال کرتی ہے۔ ساتھ پڑھا جائے تو گھر کے پیمانے کا سسٹم ڈسکو کی منظوری ہے صفر فیس کے ساتھ، اور 25 کلوواٹ سے اوپر کا سسٹم اب بھی اتھارٹی کے پاس جاتا ہے 1,000 روپے فی کلوواٹ کے ساتھ۔ ریگولیشن 3 کا کنکشن چارج الگ بل ہے۔ ریگولیشنز اسے قومی روپے میں نہیں چھاپتیں، اس لیے یہ گائیڈ عدد ایجاد نہیں کرتی۔
What to calculate while the file movesفائل چلتے ہوئے کیا حساب کریں
The application steps do not tell you whether the array is worth it. The net billing calculator takes the units you use, the size in kilowatts, the city yield and the export rate, and it prices imports on the same residential schedule as the bill calculator. It also draws the old net-metering comparison at the reported legacy surplus of Rs 25.32, so an existing agreement and a new application are not shown as the same cash flow. System price starts as a planning placeholder of about Rs 130,000 per kilowatt. That is not a quotation. Type the installer's figure.درخواست کے مراحل نہیں بتاتے کہ سرنی فائدے کی ہے یا نہیں۔ نیٹ بلنگ کیلکولیٹر آپ کے یونٹ، کلوواٹ میں سائز، شہر کی پیداوار اور برآمدی شرح لیتا ہے، اور درآمد اسی رہائشی شیڈول پر قیمت کرتا ہے جو بل کیلکولیٹر استعمال کرتا ہے۔ یہ پرانا نیٹ میٹرنگ موازنہ رپورٹ شدہ 25.32 روپے سرپلس پر بھی کھینچتا ہے، تاکہ موجودہ معاہدہ اور نئی درخواست ایک کیش فلو نہ بنیں۔ سسٹم کی قیمت تقریباً 130,000 روپے فی کلوواٹ کے منصوبہ خانے سے شروع ہوتی ہے۔ یہ کوٹیشن نہیں۔ انسٹالر کا عدد لکھیں۔
Keep the sanctioned-load rule next to any size you like the look of. The calculator will still draw a larger system if you type one, because it is an arithmetic tool, and the note on the page says the system cannot exceed sanctioned load. The five-marla guide on this site explains why a plot size is not a kilowatt size. Use that guide before you treat a roof as a number of panels, and use this one before you treat a forum checklist as the regulation.جو سائز اچھا لگے اس کے پاس منظور شدہ لوڈ کا قاعدہ رکھیں۔ کیلکولیٹر بڑا سسٹم پھر بھی کھینچے گا اگر آپ لکھیں، کیونکہ یہ حساب کا ٹول ہے، اور صفحے کا نوٹ کہتا ہے سسٹم منظور شدہ لوڈ سے بڑا نہیں ہو سکتا۔ اس سائٹ کی پانچ مرلہ گائیڈ بتاتی ہے پلاٹ کا سائز کلوواٹ کا سائز کیوں نہیں۔ چھت کو پینلوں کا عدد ماننے سے پہلے وہ گائیڈ استعمال کریں، اور فورم کی فہرست کو ریگولیشن ماننے سے پہلے یہ گائیڈ۔